Tufropes Pvt. Ltd. plans to set up a 100 tpm twines, nets & all types of ropes manufacturing unit in Daman.

May 31, 2010

Plastics & Polymers :

Status: Planning
Promoter: Tufropes Private Limited
Project Name: Twines, Nets & All types of Ropes Manufacturing Unit
Capacity: 100 tpm
Location: Near Chala, Daman, UT of Daman & Diu.
Current Status: As of May 2010, work on the project is under planning stage.


Shristi Infrastructure Dev. Corpn. is developing a 323 rooms 5 star hotel in Kolkata, project is spread over on 1 million sq. ft. of land, work on the project is underway with completion scheduled by December 2011

May 24, 2010

Hotels :

Status: Under Implementation
Completion: December 2011

Promoter: Shristi Infrastructure Development Corporation Limited
Project Name: 5 Star Hotel
Capacity: 323 Rooms
Land: 1 million sq. ft.
Location: Rajarhat in Kolkata
Current Status: As of May 2010, this 5 star hotel is part of township ‘Rajarhat’, work on the project is underway with completion scheduled by 2011, around 15 per cent project work is completed, project will be maintained by Westin Hotels & Resorts.


Shri Lakshmi Power plans to set up a new 2500 tpd cement manufacturing unit in Madhya Pradesh with an investment of Rs. 400 crore, land acquisition for the project is completed.

May 24, 2010

Cement :

Status: Planning
Promoter: Shri Lakshmi Power Limited
Project Name: Cement Manufacturing Unit
Capacity: 2500 tpd
Cost: Rs. 400 Crore
Location: Satna district of Madhya Pradesh
Current Status: As of May 2010, work on the project is under planning stage, land acquisition for the project is completed.


Divine Alloys & Power plans to set up a 8 MW WHR based CPP in Jharkhand, work on the project is likely to commence by October 2010

May 17, 2010

Thermal Power:

Status: Planning
Promoter: Divine Alloys & Power Company Limited
Project Name: WHR Based Captive Power Plant
Capacity: 8 MW
Location: Seraikela district Jharkhand.
Current Status: As of April 2010, work on the project is likely to commence by October 2010.


Irfan Agro Foods is setting up a new rice mill with an investment of Rs. 5 crore in Kerala, work on the project is underway with completion scheduled for October 2010

May 17, 2010

Food Processing:

Status: Under Implementation
Completion: October 2010
Promoter: Irfan Agro Foods Private Limited
Project Name: Rice Mill
Cost: Rs. 5 Crore
Location: Palakkad district of Kerala
Current Status: As of May 2010, work on the project is underway.


Suryansh Hotels and Resorts is setting up a 36 rooms 3 Star Hotel with an investment of Rs. 9 crore in Orissa, around 20 per cent of project work is completed with completion scheduled for November 2011

April 12, 2010

Hotels:

Status: Under Implementation
Completion: November 2011
Promoter: Suryansh Hotels and Resorts Pvt. Ltd.
Project Name: 3 Star Hotel
Capacity: 36 rooms
Architect: Rhythm Architects Pvt. Ltd., Bhubaneshwar
Cost: Rs. 9 Crore
Location: Puri, Orissa
Current Status: As of April 2010, work on the project underway, around 20 per cent of project work is completed.


CSIDCL plans to set up 150 units Gems & Jewellery SEZ on 70 acres of land in Chhattisgarh, Project will be developed on PPP basis with M/s Ramky Infrastructure Ltd.

April 5, 2010

SEZ:

Status: Planning
Promoter: Chhattisgarh State Industrial Development Corporation Limited
Project Name: Gems & Jewellery SEZ
Capacity: 150 units
Land: 70 acres
Location: Raipur, Chhattisgarh
Current Status: As of April 2010, work on the project is under planning stage. Project will be developed on Public Private Partnership (PPP) basis with M/s Ramky Infrastructure Ltd.