Tamil Nadu Govt. proposes up gradation of the Perambalur-Perali-Thanjavur Road in Tamil Nadu.

March 23, 2016

ROADS & HIGHWAY

 

Status: Planning

Promoter: Government Of Tamil Nadu, Highways And Minor Ports Department

Project: Proposes upgradation road

Location: Perambalur-Perali-Thanjavur road in Tamil Nadu

Project Details: The current status of the project could not be ascertained. According to Government sources, the project involves 2-laning with paved shoulders of Perambalur-Perali-Kunnam-Ariyalur-Keelappalur-Thiruvayaru-Kandiyur-Thanjavur section of NH 226 E (length 66.2 kms). The estimated cost of the project is Rs. 1,617 million. SPL Infrastructure is the contractor. Civil work is in progress. The project is expected to be operational by 14th July, 2017.


State Highways Authority Of Jharkhand proposes upgradation of Ghaghra-Netarhat Road in Jharkhand.

March 23, 2016

ROADS & HIGHWAYS

Status: Planning

Promoter: State Highways Authority Of Jharkhand

Project: Proposes upgradation

Location: Ghaghra-Netarhat Road in Jharkhand.

Project Details: The current status of the project could not be ascertained. According to Government sources, the estimated project cost (as per the contract) is Rs. 1,124.5 million. The length of the road is 54.3 kms. Valecha Engineering is the contractor. Civil work is in progress. The project is scheduled for completion in June 2017.


Government Of India is planning widening & strengthening of highway section in dist. Nashik, Maharashtra.

March 1, 2016

Roads & Highways

 

Status: Planning Stage

Promoter: Government Of India, Ministry Of Road Transport & Highways

Project:  Plans widening & strengthening of existing highway section

Location:  Dist. Nashik, Maharashtra

Project Details:  PBA Infrastructure, in Joint Venture has secured the contract worth Rs. 1.5775 billion for widening & strengthening of existing highway section to 2-lane with paved shoulder of NH No. 848 which includes section from km 16/000 to km 34/000, km 39/000 to 57/000 & km 62/000 to 65/600 (approximately 39.600 km) Design chainage 16.025 to 33.943, 38.945 to 56.533 & 61.515 to 65.115 (approx. 39.106 km) in dist. Nashik on Engineering, Procurement & Construction (EPC) contract – letter of award.


Government Of Tamil Nadu is planning to construct a grade separator in dist. Kanchipuram, Tamil Nadu.

May 21, 2015

Roads & Highways

Status: Planning Stage

Promoter: Government Of Tamil Nadu, Highways Department

Project: Plans to construct a grade separator

Location: Pallavaram, dist. Kanchipuram, Tamil Nadu.

Cost: The estimated cost of the project is Rs. 524.5 million.

Current Status: Tenders have been invited for construction of grade separator at intersection of Sandhai road and Kundrathur road with GST road at Pallavaram with pedestrian subway. Document sale date ends on 29th May, 2015. The last date for submission of online bids is 3rd June, 2015. The project will be completed in 33 months.


Border Roads Organization is planning to construct a highway tunnel in dist. Kupwara, Jammu & Kashmir.

March 9, 2015

Highways

Status: Planning Stage

Promoter: Border Roads Organisation

Project: Plans to construct a 6.12 Km long highway tunnel

Location: Across Sadhana Pass (Nasta Chun) on road Chokibal-Tangdhar-Chamkot road in dist. Kupwara, Jammu & Kashmir

Cost: The estimated cost of the project is Rs. 102 million.

Current Status: E-tenders have been invited seeking consultancy services for detailed feasibility study and framing up of phase-wise proposals (DPR) for construction of the project. Documents can be downloaded from 18th February, 2015 to 18th March, 2015. The last date for online submission of bids is 18th March, 2015. The project is planned for completion in 18 months.


National Highways Authority Of India is planning to upgrade from 2-laning to 4-laning of the Jabalpur-Lakhnadon section in dist. Jabalpur & dist. Seoni, Madhya Pradesh

November 13, 2014

Roads & highways

National Highways Authority Of India is planning to upgrade from 2-laning to 4-laning of the Jabalpur-Lakhnadon section in dist. Jabalpur & dist. Seoni, Madhya Pradesh.

Status: Planning Stage

Promoter: National Highways Authority Of India

Project: Plans up gradation from 2-lanes to 4-lanes

Location: Jabalpur-Lakhnadon section in dist. Jabalpur & dist. Seoni, Madhya Pradesh.

Current Status: Forest clearance has been received. The project is waiting for Government approval. Work on the project is expected to commence in March 2015 and is planned for completion in March 2017.

https://www.indianewprojects.com/blog/national-highways-authority-india-planning-upgrade-2-laning-4-laning-jabalpur-lakhnadon-section-dist-jabalpur-dist-seoni-madhya-pradesh/


PWD, Rajasthan plans for two laning of Dausa to Chaksu road & Dudu – Sambhar road including ROB in Km. 146. Project will be developed on Public Private Partnership (PPP) on DBFOT basis.

December 24, 2010

Roads

Status: Planning
Promoter: Public Works Department, Rajasthan
Project Name: Two Laning of Roads
Location: 1. Dausa to Chaksu Road (SH-2) Km 0/0 to 54/0
2. Dudu – Sambhar Road SH-2 Km. 130/0 to 156/0 including ROB in Km. 146
Current Status: As of December 2010, work on the project is under planning stage. Project will be developed on Public Private Partnership (PPP) on DBFOT basis.


NKG Infrastructure is constructing Bye-pass road on NH-88 in Himachal Pradesh. Work on the project is likely to be completed by March 2013.

December 18, 2010

Roads

Status: Under Implementation
Completion: March 2013
Promoter: NKG Infrastructure Limited
Project Name: Construction Of Bye-pass Road
Location: NH-88 [Km.140/800 to 145/800 (0/0 to 6/355)], Himachal Pradesh
Current Status: As of December 2010, work on the project is underway. Project is allotted by Himachal Pradesh Public Works Department NH Division on standalone basis.


Haryana State Roads & Bridges is implementing road upgradation of Gurgaon-Nuh-Rajasthan Border with an investment of Rs. 3478.8 millions, around 50 per cent of project work is completed with entire completion scheduled by March 2011

November 4, 2010

Roads

Status: Under Implementation
Completion: March 2011
Promoter: Haryana State Roads & Bridges Development Corporation Limited
Project Name: Road Upgradation Of Gurgaon-Nuh-Rajasthan Border SH-13 km 7.200 to 95.890 km
Cost: ` 3478.8 millions
Location: Gurgaon-Nuh-Rajasthan
Current Status: As of November 2010, work on the project is underway, around 50 per cent work is completed. The project would entail an investment of Rs. 3478.8 millions, the project is approved by National Capital Region Planning Board NCRPB (Roads).


Haryana State Roads & Bridges Development Corporation is implementing road up gradation to Dighal Beri Jahazgarh road with an total investment of Rs. 42.86 crore, work on the project is underway.

May 10, 2010

Roads

Status: Under Implementation
Promoter: Haryana State Roads & Bridges Development Corporation
Project Name: Road Upgradation of Dighal Beri Jahazgarh Road
Cost: Rs. 42.86 Crore
Location: Dighal Beri Jahazgarh Road in Jhajjar district of Haryana
Current Status: As of May 2010, work on the project is underway.