Dr. Balabhai Nanavati Hospital is implementing a renovation-cum-expansion of its super-specialty hospital in Mumbai

December 10, 2014

Hospitals

Dr. Balabhai Nanavati Hospital is implementing a renovation-cum-expansion of its super-specialty hospital in Mumbai.

Status: Under Implementation

Promoter: Dr. Balabhai Nanavati Hospital

Project: Implementing renovation-cum-expansion of super-specialty hospital

Location: S. V. Road, Mumbai, Maharashtra

Project Details: The hospital will also augment its beds capacity from 360 beds to 760 beds adjacent to the main building.

Current Status: Renovation work is in progress at main building. The project is scheduled for completion in 2018.

Advertisements

Tamilnadu Generation & Distribution Corporation is implementing the Bhavani Kattalai Barrage-3 HEP in Tamil Nadu.

September 13, 2011

Power generation

Status: Under Implementation
Promoter: Tamilnadu Generation & Distribution Corporation
Project: Bhavani Kattalai Barrage-3 Hydro Electric power project
Capacity : 2×15 MW
Cost: Rs. 3,965.9 million
Location: Cauvery River near Vendipalayam, dist. Erode, Tamil Nadu
Current Status: Weir/apron concreting & pier concreting for all the vents, power house sub structure and super structure works, second stage concreting and erection of stay rings of units 1 & 2 and second stage concreting has been completed. As of September 2011, erection of E & M equipments is in progress. Unit-1 is scheduled for completion in November 2011 and unit-2 in December 2011.


Greenpark Hotels & Resorts is constructing the Marigold 5-star hotel in Andhra Pradesh.

September 13, 2011

Hotels

Status: Under Implementation
Promoter: Greenpark Hotels & Resorts Ltd
Project: “Marigolr”5 Star Hotel (187 rooms)
Cost: Rs. 70 million
Location: in dist. Hyderabad, Andhra Pradesh
Current Status: As of August 2011, the civil work was in progress. The project is scheduled for completion in 2012.


Kolkata Metro Rail Corporation is implementing a metro line from Baranagar-Barrackpore and Dakshineswar.

September 13, 2011

Railways

Status: Under Implementation
Promoter: Kolkata Metro Rail Corporation
Project: Metro Rail
Cost: Rs. 20,696 million
Contractor: Consolidated Construction Consortium, Chennai and Sam (India) Infrastructure, New Delhi
Location: Baranagar-Barrackpore and Dakshineswar in Kolkata, West Bengal (14.50 kms)
Current Status: As of August 2011, the work on the project commenced in March 2011 and the completion date of the project is to be finalized. The scope of work includes execution of design & construction of PSC viaduct, embankment and stations including E&M works in connection with extension of metro railway line Naopara (excluding) Baranagar-Dakshineswar of Kolkata Metro.


Tamilnadu Newsprint & Papers is implementing a cement manufacturing project in Tamil Nadu.

September 13, 2011

Cement

Status: Under Implementation
Promoter: Tamilnadu Newsprint & Papers Limited
Project: Cement manufacturing Unit
Capacity: 600 TPD
Location: Kagithapuram, dist. Karur, Tamil Nadu
Current Status: As of August 2011, civil work completed. Erection of machinery is under progress and the project is scheduled for completion in some time in 2011.


Sunglow Suitings is implementing a synthetic fabric manufacturing expansion in dist. Bhilwara, Rajasthan.

September 6, 2011

Textiles

Status: Under Implementation
Promoter: Sunglow Suitings PvtLtd
Project: synthetic fabric expansion project
Product: synthetic fabric (capacity expansion by Installation of additional 50 looms)
Location: RIICO Industrial Area, dist. Bhilwara, Rajasthan.

Current Status: As August 2011, civil work is under progress and the project is scheduled for completion in April 2012.


Hindoostan Mills expanding calender rollers manufacturing capacity in Maharashtra.

September 6, 2011

Industrial Plant and Machinery

Status: Under Implementation
Promoter: Hindoostan Mills Ltd
Project: Expansion
Product: calender rollers
Location: Karad, dist. Satara, Maharashtra

Current Status: As of August 2011, equipment supplier appointed. Civil work is in progress. The project is scheduled for completion in September 2011.