Polygenta Technologies has set up 30,000 tpa Polyester Filament Yarn unit with an investment of Rs. 270 crore in Maharashtra.

February 19, 2011

Textiles

Status: Commissioned
Completion: February 2011
Promoter: Polygenta Technologies Limited
Project Name: Polyester Filament Yarn
Capacity: 30,000 TPA
Cost: Rs. 270 crore
Location: Dindori, Nashik, Maharashtra
Current Status: As of February 2011, project is commissioned.

Advertisements

Space India Builders & Developers is developing residential complex ‘Venkat Heritage’ in Maharashtra. Work on the project is likely to be completed by August 2011.

February 19, 2011

Real Estate

Status: Under Implementation
Completion: August 2011
Promoter: Space India Builders & Developers
Project Name: ‘Venkat Heritage’ Residential Complex
Capacity: 5 buildings of G +4 floors & 2 buildings of G +3 floors
Location: New Panvel, Tembhode, Maharashtra
Current Status: As of February 2011, work on the project is underway.


Electronics Corpn. of Tamil Nadu plans to set up IT/ITES SEZ on 245.17 acres in Madurai.

February 19, 2011

SEZ

Status: Planning
Promoter: Electronics Corporation Of Tamil Nadu Limited
Project Name: IT/ITES SEZ
Land: 245.17 Acres
Location: Vadapalanji, Madurai district, Tamil Nadu
Current Status: As of February 2011, work on the project is under planning stage.


Maharashtra State Power Generation Company plans renovation and modernization of 210 MW Nashik Thermal Power Station Unit-3

February 19, 2011

Thermal Power

Status: Planning
Promoter: Maharashtra State Power Generation Company Limited
Project Name: Maharashtra State Power Generation Company Project Of Nashik Thermal Power Station Unit-3
Capacity: 210 MW
Location: Nashik
Current Status: As of February 2011, work on the project is under planning stage. EoI’s were invited for Providing Consultancy Services for Implementation of Indo-German Energy Efficiency & Life Extension Programme for Renovation and Modernization Project of Nashik Thermal Power Station Unit-3 (210MW), last date of submission: 31-March-2011.


RAK Ceramics India plans to set up tiles manufacturing unit with an investment of Rs. 600 crore in Gujarat.

February 12, 2011

Ceramics

Status: Planning
Promoter: RAK Ceramics India Private Limited
Project Name: Tiles Manufacturing Unit
Cost: Rs. 600 Crore
Location: Ahmadabad, Gujarat
Current Status: As of February 2011, work on the project is under planning stage.


UPJVNL plans to set up 3.75 MW Khairi small hydel power plant in Uttar Pradesh.

February 7, 2011

Hydel Power

Status: Planning
Promoter: Uttar Pradesh Jal Vidyut Nigam Limited
Project Name: Khairi Small Hydel Power Plant
Capacity: 3.75 MW
Location: Sharanpur, Uttar Pradesh
Current Status: As of February 2011, work on the project is under planning stage. Bids were invited for development & implementation of small hydro power project on BOOT basis, last date of submission: 30 March, 2011.


Lady Hardinge Medical College plans to construct hospital infrastructure in Delhi.

February 7, 2011

Hospital Infrastructure

Status: Planning
Promoter: Lady Hardinge Medical College & Associated Hospitals (LHMC)
Project Name:
• Construction of Hospital Buildings, Academic Block, Student’s Hostel with associated Services Under phase-1 for Comprehensive Redevelopment Plan
• Construction of Residential units and RMO Accommodation with Associated Services under phase-1 for Comprehensive Redevelopment Plan

Consultant: HSCC (India) Ltd.
Location: New Delhi, Delhi
Current Status: As of February 2011, work on the project is under planning. Bids were invited for Comprehensive Redevelopment Plan under phase I, last date of submission: 28 February, 2011.