Ami Lifesciences proposes expansion of its synthetic organic chemicals manufacturing unit in dist. Vadodara, Gujarat.

June 6, 2015

Organic, Inorganic & Speciality Chemical

Status: Planning

Promoter: Ami Lifesciences

Project: Proposes expansion of its synthetic organic chemicals manufacturing unit (viz. pharmaceutical bulk drugs & drug intermediates)

Location: Padra, dist. Vadodara, Gujarat

Capacity: To be expanded from 65.70 TPM to 131.60 TPM

Cost: The estimated cost of the project is Rs. 87.046 million

Environmental Consultant: Envisafe Environment Consultants.

Project Details: According to MoEF sources, total plot area is 23,760 Sq. mtrs (Existing 10270 Sq. mtrs and 13490 Sq. mtrs for expansion). The unit currently manufactures 2 TPM 1- Acetyl Naphthalene, 1 TPM 2- Acetyl Naphthalene, 6 TPM itopide HCl, 1.20 TPM loxapine succinate, 0.30 TPM amoxapine, 6 TPM venlafaxine, 6 TPM progunil HCl, 6 TPM CB-2-L-Valine, 0.60 TPM nateglinide, 0.60 TPM quetiapine, 24 TPM carbomazepin and 12 TPM oxacarbomazepin. The expansion will involve addition of new products namely, 30 TPM pure rutin, 20 TPM quercetin, 15 TPM doxofylline, 15 TPM troxerutin, 5 TPM ambroxol hydrochloride and its intermediate (2 Amino 3, 5-dibromo Benzaldehyde), 5 TPM itopride hydrochloride, 3 TPM febuxostat, 3 TPM fexofenadine hydrochloride, 3 TPM N-Methyl-1-Naphthyl methylamine HCI, 3 TPM acebrophylline, 3 TPM diacerein, 2.30 TPM crude diacerein, 2 TPM iron polymaltose, 2 TPM choline fenofibrate, 2 TPM tranexamic acid, 2 TPM flavoxate hydrochloride & intermediate (3- Methylflavone-8-Carboxylic Acid), 2 TPM S-Metoprolol succinate, 2 TPM betahistine dihydrochloride, 1 TPM xanthinol nicotinate, a 1 TPM fenofibrate, 1 TPM pamabrom, 1 TPM venlafexine hydrochloride, 1 TPM tadalafil, 1 TPM tapentadol hydrochloride, 1 TPM linezolid, 1 TPM eslocarbazepine acetate, 1 TPM sevelamer carbonate, 1 TPM sevelamer hydrochloride, 0.50 TPM desmethyl venlafexine succinate monohydrate, 0.50 TPM alpha lipoic acid, 0.50 TPM L-Methylfolate, 0.25 TPM dapoxetine hydrochloride, 0.20 TPM tauroursodeoxycholic acid, 0.10 TPM indapamide, 0.10 TPM azilsartanmedoxomil potassium salt, 0.10 TPM proguanilhydrchloride and 00.5 TPM olopatadine hydrochloride.

Water requirement from ground water source will be increased from 34.53 cu. mtrs/day to 181 cu. mtrs/day after expansion. Effluent generation will be increased from 9.35 cu. mtrs/day to 79.5 cu. mtrs/day after expansion. Highly concentrated effluent will be sent to captive incinerator for incineration. Remaining effluent (70 m3/day ) will be treated in the ETP comprising primary, secondary and tertiary treatment. Treated effluent will be sent to CETP for further treatment. ETP sludge, inorganic residue and incineration ash will be sent to TSDF. Spent carbon, organic residue will be sent to incinerator.


Anupam Rasayan India is implementing a chloro benzene compounds manufacturing project in dist. Surat, Gujarat.

June 6, 2015

Organic, Inorganic & Specialty Chemicals

Status: Under Implementation

Promoter: Anupam Rasayan India

Project: Setting up a chloro benzene compounds manufacturing project

Location: Sachin, dist. Surat, Gujarat.

Environmental consultant: Aqua-Air Environmental Engineers is the environmental consultant.

Current Status: Civil work is in progress and the project is scheduled for completion in May 2015.


Government Of India is planning a railway design centre in dist. Ahmedabad, Gujarat.

June 6, 2015

SCIENTIFIC & TECHNICAL SERVICES

Status: Planning Stage

Promoter: Government Of India

Project: Plans a railway design centre at NID Campus

Location: Dist. Ahmedabad, Gujarat

Project Details: An MoU was signed between Ministry of Railways and National Institute Of Design (NID) to develop the centre. The centre will be operated by the interest accrued on the endowment fund of Rs. 100 million. The endowment fund for this purpose is being deposited by the Ministry of Railways. Centre will be developing new concepts in design & innovations in various fields of railway functioning, like passenger amenities at station areas and in trains, improvement to coach layouts, environmental issues, various maintenance tools, IT & communication issues etc. The MoU will be for a period of 10 years, which can be further extended as mutually agreed.


Cochin Shipyard is planning a shipyard in dist. Kutch, Gujarat.

May 21, 2015

Ports & Harbours

Status: Planning Stage

Promoter: Cochin Shipyard

Project: Plans a shipyard

Location: Tuna region of Kandla Port, dist. Kutch, Gujarat

Project Detail: The project will spread over 310 hectares. Global expression of interest has been invited for selection of consultant for conducting techno-economic feasibility study (TEFS) for setting up the shipyard and ancillary industries. Kandla Port Trust (KPT) had recently invited Global Expression of Interest for setting up Industries directly requiring waterfront at Port Based Multi-Product Special Economic Zone (PBMSEZ) at Tuna, Gujarat on 5000 hectares (3600 hectares at Kandla & 1400 hectares at Tuna). As a part of CSL’s overall growth agenda, the possibility of setting up a shipyard at Tuna, is being looked into. It is proposed to construct dry docks & allied facilities in order to cater to the building & repair demands of vessels up to Very Large Crude Carriers (VLCC) size. Setting up of ancillary industries in connection with ship building / repair, ship breaking facility, possibility of accommodating Ultra Large Crude Carriers (ULCC) etc are to be explored.

The scope of the consultant would be:
(i) preliminary engineering (pre-feasibility) study,
(ii) preparation of an indicative layout, identification and finalization of various infrastructure facilities & finalize the indicative layout incorporating the identified requirements,
(iii) setting up ship building/ ship repair/ ship breaking facility
(iv) preparation of block estimate for the infrastructure facilities,
(v) identification of the further studies and investigations to be undertaken during the DPR stage
(vi) Identification and listing of Coastal Regulation Zone (CRZ)/ environmental clearance & other statutory/ administrative clearances required
(vii) preliminary market analysis,
(viii) economic analysis &
(xi) techno-economic feasibility study report.


Gujarat State Aviation Infrastructure Company is planning an airstrip in dist. Morbi, Gujarat.

April 13, 2015

Airports

Status: Planning Stage

Promoter: Gujarat State Aviation Infrastructure Company

Project: Plans a 1.2 Km airstrip

Location: Dist. Morbi, Gujarat.

Current Status: Tender is yet to be invited for selection of contractor. The project is in planning stage. According to media reports, transfer of land is in progress.


Airports Authority Of India is planning to construct a cargo terminal in dist. Surat, Gujarat.

March 9, 2015

Airports

Status: Announcement/Conceptual Stage

Promoter: Airports Authority Of India

Project: Plans to construct a cargo terminal

Location: at Dumas Road, dist. Surat, Gujarat

Project Details: The project is in preliminary stage. Airports Authority of India (AAI) has given in-principle approval for setting up the cargo terminal. According to media sources, the terminal is to boost south Gujarat’s industrial sector including textile, chemical, diamonds, horticulture and ancillary industries. The cargo terminal is expected to ease the movement of precious cargo including diamonds, gold and jewellery from Surat. AAI gave an in-principle approval for the cargo terminal with a handling capacity of around 5,000 tonnes. The decision on inviting tender applications will be taken by the regional headquarters at Mumbai.

Current Status: The Authority is still awaiting the final go-ahead on the cargo terminal.


Adi Finechem is planning a speciality products manufacturing project in dist. Ahmedabad, Gujarat.

February 19, 2015

Chemicals

Status: Planning Stage
Promoter: Adi Finechem
Project: Plans 40 TPA speciality products manufacturing unit
Location: Village Chekhala, dist. Ahmedabad, Gujarat
Project Details: The land area is 2 acres and the estimated cost of the project is Rs. 400 million.
Current Status: The project is waiting for environmental clearance.


Follow