SJVNL plans to set up 40 MW Dhaulasidh HEP with investment of Rs. 400 crore in Himachal Pradesh.

February 19, 2011

Hydel Power

Status: Planning
Promoter: Satluj Jal Vidyut Nigam Limited
Project Name: Dhaulasidh HEP
Capacity: 40 MW
Cost: Rs. 400 crore approx.
Location: Sanotu Tehsil of District Hamirpur in Himachal Pradesh.
Current Status: As of February 2011, work on the project is under planning stage.


ACME Tele Power is setting up 15 MW photovoltaic solar power plant in Gujarat.

February 12, 2011

Non-conventional Power

Status: Under Implementation
Promoter: ACME Tele Power Ltd.
Project Name: Photovoltaic Solar Power Plant
Capacity: 15 MW
Location: Gujarat
Current Status: As of February 2011, work on the project is underway. ACME Tele Power Ltd. Signs Module Supply Agreement with First Solar Inc for photovoltaic solar power project in India.


TNSAMB plans to set up modern terminal market complex in Tamil Nadu.

February 12, 2011

Commercial Complex

Status: Planning
Promoter: Tamil Nadu State Agricultural Marketing Board (TNSAMB)
Project Name: Modern Terminal Market Complex (TMC)
Location: Chennai, Tamil Nadu
Current Status: As of February 2011, work on the project is under planning stage. Request for Qualifications were invited for Design, Engineering, Financing, Procurement, Construction, Operation and Maintenance of the project.


Sita Shree Food Products plans to set up 500 tpd soyabean oil extraction unit with an investment of Rs. 450 million in Madhya Pradesh. Work on the project is likely to be completed by September 2011.

February 12, 2011

Food Processing

Status: Planning
Completion: September 2011
Promoter: Sita Shree Food Products Limited
Project Name: Soyabean Oil Extraction Unit
Capacity: 500 TPD
Cost: 450 million
Location: near Shipra, Indore, Madhya Pradesh
Current Status: As of February 2011, work on the project is under planning stage. Land is acquired for the project.


Ginger Hotels is setting up 100 rooms 5-star hotel in Tamil Nadu.

February 12, 2011

Hotels

Status: Under Implementation
Promoter: Ginger Hotels
Project Name: 5-star Hotel
Capacity: 100 rooms
Location: Tirupur, Tamil Nadu
Current Status: As of February 2011, work on the project is underway.


S A L Steel plans to set up 2.5 mtpa cement manufacturing unit in Gujarat. MoEF clearance for the project is awaited.

February 7, 2011

Status: Planning
Completion: December 2012
Promoter: S A L Steel Limited (Group Company of Shah Alloys Ltd.)
Project Name: Cement Manufacturing Unit
Capacity: 2.5 million tpa
Location: Gandhidham, dist. Kutch, Gujarat
Current Status: As of January 2011, work on the project is under planning stage. Project is waiting for MoEF clearance.


MCC PTA India Corporation has expanded capacity of its purified terephthalic acid manufacturing unit.

July 12, 2010

Chemicals :

Status: Commissioned
Promoter: MCC PTA India Corporation Private Limited
Project Name: Expansion of Purified Terephthalic Acid Manufacturing Unit
Capacity: From 470,000 tpa to 800,000 tpa
Location: Haldia Plant, dist. East Midnapore, West Bengal
Current Status: As of June 2010, project is completed.


Ista Hotels expansion of hotel project in Hyderabad is kept on hold.

July 12, 2010

Hotels :

Status: On hold
Promoter: Ista Hotels
Project Name: Expansion of Hotel
Location: Gachibowli near Hyderabad in Andhra Pradesh
Current Status: As of June 2010, work on the project is kept on hold


Piramal Suntek Realty is setting up residential complex ‘Signia Oceans’ in Maharashtra. Pratibha Industries are the contractors for the project, project comprises of total 72 flats.

July 12, 2010

Real Estate:

Status: Under Implementation
Completion: July 2012
Promoter: Piramal Suntek Realty Pvt. Ltd.
Project Name: Residential Complex ‘Signia Oceans’
Contractor: Pratibha Industries Ltd.( the flagship company of the Pratibha Group)
Capacity: 72 Flats
Location: Airoli, Navi Mumbai in Maharashtra
Current Status: As of July, 2010 work on the project is underway, project includes ground floor, a podium and 27 floors.


Shree Siddhivinayak Cotspin is expanding capacity from 15000 to 22000 spindles in Maharashtra.

July 12, 2010

Textiles:

Status: Under Implementation
Promoter: Shree Siddhivinayak Cotspin Private Limited
Project Name: Expansion Cotton Yarn
Capacity: from 15000 to 2200 spindles
Location: Kolhapur, Maharashtra
Current Status: As of July, 2010 work on the project is underway.