Chinteshwar Steel’s 12 MW thermal power plant kept on hold

October 22, 2010

Thermal Power

Status: On Hold
Promoter: Chinteshwar Steel Pvt. Ltd.
Project Name: Coal Based Power Plant
Capacity: 12 MW
Location: Kamptee, Nagpur
Current Status: As of August 2010, project is kept on hold.


Bajaj Hindusthan plans to set up a 80 MW coal based power plant in Uttar Pradesh, company has applied for various necessary approvals.

February 6, 2010

Thermal :

STATUS: Planning
PROMOTER: Bajaj Hindusthan Ltd.
PROJECT NAME:Coal Based Power Plant
CAPACITY: 80 MW
LOCATION:Khamberkhera in Lakhimpurkheri district of Uttar Pradesh
CURRENT STATUS:As of January 2010, work on the project is under planning stage, company has applied for NOC for power facility extension, technical bids are received from 8 parties for supply of Boilers & TG sets. Application for coal linkage for all units has been submitted to ministry of coal. Company is under negotiation for overseas long term coal supply & also scouting for coal mine acquisition.


Kribhco plans to set up a 1320 MW coal based power plant in Bihar

January 30, 2010

Thermal Power:

STATUS:Planning
PROMOTER:Krishak Bharti Co-operative Ltd. (Kribhco)
CO-PROMOTER:Bihar State Electricity Board (BSEB)
PROJECT NAME:Coal Based Power Plant
CAPACITY:1320 MW
LOCATION:Chausa in Buxar district of Bihar
CURRENT STATUS:As of January 2010, work on the project is under planning stage


Bhoruka Power Corporation plans to set up a 2 x 150 MW coal based power plant in Karnataka, company is waiting for land allotment for the project

January 9, 2010

Thermal:

STATUS: Planning
PROMOTER: Bhoruka Power Corporation Ltd. (BPCL)
PROJECT NAME::Coal Based Power Plant
CAPACITY: 2 x 150 MW
LOCATION: Karwar, Karnataka
CURRENT STATUS:As of December 2009, work on the project is under planning stage, company is waiting for land allotment for the project.


Grace Industries plans to set up a 2×50 MW coal based power plant at Maharashtra

January 2, 2010

Thermal:

STATUS: Planning
PROMOTER: Grace Industries Limited
PROJECT NAME:Coal Based Power Plant
CAPACITY: 2 x 50 MW
CONSULTANT: Cethar Consulting Engineers (P) Ltd.
LOCATION:MIDC area Tadali, District Chandrapur, Maharashtra
CURRENT STATUS:As of November 2009, work on the project is under planning stage.
CURRENT STATUS:As of November 2009, work on the project is under planning stage.


Shantha Steel & Power is implementing a 52 MW coal based power plant in Karnataka, work on the project is likely to be completed by December 2010

December 26, 2009

Thermal:

STATUS: Under Implementation
COMPLETION: December 2010
PROMOTER: Shantha Steel & Power Pvt. Ltd.
PROJECT NAME::Coal Based Power Plant
CAPACITY: 52 MW (Phase I – 10 MW)
COST: Rs. 450 million for Phase I
LOCATION: in Koppal, Karnataka
CURRENT STATUS: As of December 2009, work on the project is underway.