Bhabha Atomic Research Centre is planning to construct pre-engineered buildings in Karnataka.

March 1, 2016

Prefabricated Construction

 

Status: Planning Stage

Promoter: Bhabha Atomic Research Centre

Project: Plan to construct pre-engineered buildings

Location: Ullarthi Project Site, Challakere, dist. Chitradurga, Karnataka

Project Details:  EoI cum pre-qualification tenders have been invited for construction of project office building, store building & work shop building (pre-engineered buildings) for SMF at Ullarthi project site. The estimated cost of the project is Rs. 110 million. Only Indian firms are allowed to participate. The scope of work for pre-engineered buildings includes detailed design, engineering, drawings, supplying, fabricating and erecting pre-engineered buildings. Scope of work also includes providing detailed foundation designs, drawings & execution of foundation for supporting structural columns, construction of all civil items, internal water supply & sanitary items, external sewer line, roads, storm water drainage, internal electrical & telephone conduits, switch boxes etc, supply & erection of EOT cranes, external & internal electrical works which includes 11KV/415 V compact substation, HT cable, power panel, lighting distribution boards, LT power cable, power wiring, telephone conduits, switch boxes etc. Document sale ends on 29th January, 2016. The last date for submission of bids is 3rd February, 2016. The project is to be completed in 12 months from the date of award of tender.

Advertisements

Azure Power India is implementing a solar photovoltaic power project in dist. Chitradurga, Karnataka.

December 10, 2014

NON CONVENTIONAL ENERGY

Status:  Under Implementation

Promoter:  Azure Power India

Project: Setting up a  solar photovoltaic power project

Capacity: 10 MW

Location: Hiriyur Taluka, dist. Chitradurga, Karnataka.

Current Status:  PPA has been signed with Bangalore Electricity Supply Company (BESCOM). Civil work & panel installation work is in progress.


Laxmi Ganpathy Sponge Iron & Mines plans to set up 2×100 tpd sponge iron unit along with 4 MW WHRB power plant in Karnataka.

May 7, 2011

Metallurgy

Status: Planning
Promoter: Laxmi Ganpathy Sponge Iron & Mines Private Limited
Project Name: Sponge Iron Unit
Capacity: 2×100 TPD Sponge Iron & 4 MW WHRB Power Plant
Location: Village Muradi, Chitradurga, Karnataka
Current Status: As of May 2011, work on the project is under planning stage.