Government Of India has inaugurated an apparel and garment making unit in Tripura

May 3, 2016

Textile

Status: Commissioned

Promoter: Government Of India, Ministry Of Textiles

Project: Inaugurated an apparel and garment making unit

Location: Bodhjungnagar Industrial Growth Centre, Agartala, Tripura

Project Details: The unit was inaugurated on 8th April, 2016. The project will develop entrepreneurship through various capacity building measures and also train the people to work efficiently on high-end garment machines. It will help to develop an ecosystem which will trigger further investments and employment in the state.


Deepak Spinners has commissioned an expansion of its synthetic yarn unit in Madhya Pradesh

April 5, 2016

Textile

Status: Commissioned

Promoter: Deepak Spinners

Project: Commissioned an expansion of its synthetic yarn manufacturing unit

Capacity: (Expansion from 38,736 spindles to 52,848 spindles)

Location: Village Pagara, dist. Guna, Madhya Pradesh.

Project Details: The project entailed installation of 14,112 spindles together with related machinery and accessories in the existing plant premises at a capital cost of Rs. 620 million. The project has been completed & commercial production started in February 2016.


Sutlej Textiles & Industries has commissioned the upgraded cotton yarn spinning unit in Himachal Pradesh

January 8, 2016

Basic textiles manufacturing

Project Status: Commissioned

Promoter: Sutlej Textiles & Industries, a part of K K Birla Group

Project: Upgraded cotton yarn spinning unit

Location: at Unit: Birla Textile Mills, Village Bhatauli Khurd, dist. Solan, Himachal Pradesh

Project Details: The unit manufactures 83,376 spindles of cotton yarn, blended yarn, dyed yarn etc. The scope of upgradation involved addition of a new technology equipment in the existing plant. The estimated cost of the project is Rs. 290 million. The upgradation was commissioned in December 2015.


Shreyans Textiles is implementing a readymade garments manufacturing project in Surat, Gujarat.

December 27, 2014

Textiles

Status: Under Implementation
Promoter: Shreyans Textiles
Project: Setting up a readymade garments, knitted garments & knitted fabrics manufacturing unit
Location: Hojiwala Industrial Estate dist. Surat, Gujarat
Project Cost: The total cost of the project is Rs. 140 million.
Project Details: The project will spread over 3,600 Sq.Mtrs of acquired land. Machinery has been ordered from Germany & the Republic of China. Karl Mayer Textilmaschinenfabrik GmBH is the major equipment supplier.
Curernt Status: Civil work is under progress. Work on the project commenced in October 2014 & is scheduled for completion in January 2015.


DCM Shriram Industries is planning an expansion of its rayon tyre cord, dipped fabric, carbon disulphide, sodium sulphate manufacturing project in Rajasthan.

December 10, 2014

Textile

Status: Planning Stage

Promoter: DCM Shriram Industries, belonging to the Shriram Group

Project: Planning an expansion of its rayon tyre cord, dipped fabric, carbon disulphide, sodium sulphate manufacturing unit and captive power plant

Location: Village Ladpura, dist. Kota, Rajasthan

Cost: The estimated cost of the project is Rs. 1.63 billion

Project Details: The project spread over 325,000 sq. mtrs comes under the Shriram Rayons unit. Kadam Environmental Consultants is the consultant. The capacity of rayon tyre cord is augmented from 23 TPD to 36 TPD, dipped fabric from 20 TPD to 35 TPD, carbon disulphide from 15 TPD to 20 TPD, sodium sulphate (by product) from 27 TPD to 40 TPD, sodium sulphide (15% solution) (by product) from 2 TPD to 2.7 TPD & the coal and agro waste (husk)-based CPP from 7.2 MW to 11.2 MW.

Current Status: The project is waiting for environmental clearance. Work on the project is expected to commence in 2015 & planned for completion in 2 years thereafter.


High Tech Knitwear is implementing a grey fabric manufacturing project in dist. Bharuch, Gujarat.

September 29, 2014

Textile

Status: Under Implementation

Promoter: High Tech Knitwear is implementing a 3 million mtrs/month grey fabric manufacturing project .

Location: Village Panjroli, dist. Bharuch, Gujarat

Project Details: The project will spread over 25,000 sq. mtrs . The project will come up in three phases. 1 million mtrs/ month of grey fabric will be manufactured in each phase. Imported machinery has been ordered for phase-II.

Current Status:  Civil work is in progress for phase-II, scheduled for completion in December 2014. Phase-III is in planning stage. Work on phase-III is expected to commence in January 2015 & is planned for completion in May 2015. Phase-I was commissioned in May 2014.


BKS Textiles is implementing a woven fabrics manufacturing project in dist. Tiruppur, Tamil Nadu.

August 4, 2014

Textiles

Status: Under Implementation
Promoter: BKS Textiles
Project: Woven fabrics manufacturing project
Location: Palladam Hi-Tech Weaving Park, dist. Tiruppur, Tamil Nadu.
Project Detail: The project will involve installation of 24 Rapier looms in addition to the existing 60 Sulzer looms in the existing plant premises.
Current Status: Civil work is nearing completion. The project is scheduled for completion in Q3 2014.