Kerala State Electricity Board is constructing a substation with transformer and double circuit line.


Power transmission

Status: Under Implementation
Promoter: Kerala State Electricity Board
Project: Construction of a 220/110 KV substation with 1×200 MVA transformer and 28.5 km 220 KV double circuit line.
Location: From Pothencode to Kattakkada, dist. Thiruvananthapuram, Kerala.
Current Status: As of November 2012, civil work is in progress. The project is scheduled for completion on 31st December 2012.