GAIL India is implementing a gas pipeline across UP and Uttarakhand.


OIL & GAS

Status: Under Implementation
Promoter: GAIL India Ltd
Project: pipeline for transportation of gas
Cost: Rs. 2500 million
Location: Karanpur – Moradabad – Kashipur – Rudrapur in the states of Uttar Pradesh and Uttarakhand
Current Status: The project entails laying of 100 Kms of 12 inch diameter and another 175 Kms of spurlines of varying diameter totaling 275 Kms. As of December 2011, the work on the project commenced in 2010 and is scheduled for completion in March 2012.