Sunglow Suitings is implementing a synthetic fabric manufacturing expansion in dist. Bhilwara, Rajasthan.

September 6, 2011

Textiles

Status: Under Implementation
Promoter: Sunglow Suitings PvtLtd
Project: synthetic fabric expansion project
Product: synthetic fabric (capacity expansion by Installation of additional 50 looms)
Location: RIICO Industrial Area, dist. Bhilwara, Rajasthan.

Current Status: As August 2011, civil work is under progress and the project is scheduled for completion in April 2012.


Shri Kalyan Buildmart is constructing the Shri Kalyan Buildmart office complex in Rajasthan.

September 6, 2011

Commercial Complexes

Status: Under Implementation
Promoter: Shri Kalyan Buildmart
Project: Shri Kalyan Buildmart Office complex
Product: Office complex G+7 Floor (65 units)
Location: Chainpura, near Jawahar Circle, Teshil Sanganer, dist. Jaipur, Rajasthan.

Current status: Architect has been appointed. As of August 2011, the work on the project is under progress and scheduled for completion in December 2013.


Jay Ushin plans to set up a lock and key, handle bar manufacturing unit in Rajasthan.

August 6, 2011

Automotive Components

Status: Planning
Promoter: Jay Ushin Limited
Project Name: Lock And Key, Handle Bar (For Automobiles) Manufacturing Unit
Capacity: Lock And Key, Handle Bar For Automobiles – 2 Million-Sets Per Year
Location: Alwar, Rajasthan.
Current Status: As of August 2011, land has been acquired for the project.


Jain Irrigation Systems is implementing solar water pumping system manufacturing unit in Rajasthan.

July 30, 2011

Other Engineering Products NES

Status: Under Implementation
Promoter: Jain Irrigation Systems Limited
Project Name: Solar Water Pumping System Manufacturing Unit
Location: Alwar, Rajasthan
Current Status: As of July 2011, civil works are underway.


Puja Spintex is implementing expansion of its synthetic fabrics manufacturing unit in Rajasthan.

June 18, 2011

Textiles & Textile products

Status: Under Implementation
Promoter: Puja Spintex Private Limited
Project Name: Expansion Of Synthetic Fabrics Manufacturing Unit
Capacity: Synthetic Fabrics – from: 2.5-million mtrs per month to 4-million mtrs per month
Cost: Rs. 50 million
Location: Bhilwara, Rajasthan
Current Status: As of June 2011, civil work is in progress.


Sunbeam Auto is setting up aluminum alloy die casting manufacturing unit in Rajasthan.

May 7, 2011

Metallurgy

Status: Under Implementation
Completion: September 2011
Promoter: Sunbeam Auto Private Limited
Project Name: Aluminum Alloy Die Casting Manufacturing Unit
Location: Alwar, Rajasthan
Current Status: As of May 2011, work on the project is underway.


Uma Polymers plans to set up flexible packaging material manufacturing unit in Rajasthan.

April 30, 2011

Plastics

Status: Planning
Promoter: Uma Polymers Limited
Project Name: Flexible Packaging Material Manufacturing Unit
Location: Jodhpur, Rajasthan.
Current Status: As of April 2011, work on the project is under planning stage.


Prathista Industries is setting up organic granules & organic manures (liquid form) manufacturing unit with an investment of Rs. 60 crore in Rajasthan

April 30, 2011

Fertilizers

Status: Under Implementation
Promoter: Prathista Industries Limited
Project Name: Organic Granules & Organic Manures (Liquid Form) Manufacturing Unit
Capacity: Organic Granules-100 tpm & Organic Manures-30 tpm
Cost: Rs. 60 Crore
Location: Jaipur, Rajasthan
Current Status: As of April 2011, work on the project is underway.


RSWM Ltd. plans to set up 100,000 spindles cotton yarn unit in Rajasthan.

April 23, 2011

Textiles

Status: Planning
Promoter: RSWM Limited
Project Name: Cotton Yarn
Capacity: 100,000 Spindles
Location: Rajasthan
Current Status: As of April 2011, work on the project is under planning stage.


Ajanta Polymers is setting up 300 tpm synthetic organic chemicals manufacturing unit

March 12, 2011

Chemicals

Status: Under Implementation
Completion: July 2011
Promoter: Ajanta Polymers Private Limited
Project Name: Synthetic Organic Chemicals Manufacturing Unit
Capacity: 300 TPM
Location: Matsya Industrial Area, Alwar, Rajasthan
Current Status: As of March 2011, 60 per cent of project work is completed.