Sona Sati Organics is implementing a molasses based distillery in Bihar.

August 13, 2011

Distilleries

Status: Under Implementation
Promoter: Sona Sati Organics Private Limited
Project Name: Molasses based distillery in Gopalganj
Location: Rajapatti Kothi, Gopalganj, Bihar
Capacity: 45 KLD of Ethanol and extra neutral alcohol

Current Status: As of July 2011, civil work is under progress. The Project is scheduled for completion in 2012.


Lumbini Beverages has completed expansion of its carbonated beverages, PET bottle and juice based drinks processing unit in Bihar.

July 30, 2011

Beverages

Status: Commissioned
Promoter: Lumbini Beverages Private Limited
Project Name: Expansion Of Carbonated Beverages, PET Bottle, Juice Based Drinks Processing Unit
Location: Vaishali, Bihar
Current Status: As of July 2011, the project stands commissioned.


Ganesh Steel Impex is planning a profiles, structures, ingots production unit in district Muzaffarpur, Bihar.

July 2, 2011

Primary Steel Production

Status: Planning
Promoter: Ganesh Steel Impex Limited
Project Name: Profiles, Structures, Ingots Production Unit
Location: Muzaffarpur, Bihar

Current Status: As of June 2011, the project is under planning stage.


Jhunjhunwala Oil Mills plans for expansion of its rice mill in district Kaimur, Bihar.

July 2, 2011

Processed / Packaged Foods

Status: Planning
Completion: April 2013
Promoter: Jhunjhunwala Oil Mills Limited
Project Name: Expansion Of Rice Mill
Capacity: From 8 TPH To 32 TPH
Location: Kaimur (Bhabua), Bihar

Current Status: As of June 2011, the project is waiting for clearances. Land has been acquired.


Ultratech Cement is planning a cement manufacturing unit in Bihar.

June 13, 2011

Cement & Concrete Products

Status: Planning
Promoter: Ultratech Cement Limited
Project Name: Cement Manufacturing Unit
Location: Patna, Bihar
Current Status: As of June 2011, work on the project is under planning stage.


Tathagata Bio Energy plans to set up 12 MW biomass power plant in Bihar.

May 7, 2011

Non-conventional Power

Status: Planning
Promoter: Tathagata Bio Energy Private Limited
Project Name: Biomass Power Plant
Capacity: 12 MW
Location: Gaya, Bihar
Current Status: As of May 2011, work on the project is under planning stage.


Nibhi Industries has set up 1, 00, 000 mtpa asbestos cement sheet manufacturing unit with an investment of Rs. 31 crore in Bihar.

March 5, 2011

Cement

Status: Completed
Promoter: Nibhi Industries Private Limited
Project Name: Asbestos Cement Sheet Manufacturing Unit
Completion: March 2011
Capacity: 1, 00, 000 MTPA
Cost: Rs. 31 Crore
Location: Bhojpur, Bihar
Current Status: As of March 2011, work on the project is completed.


Bihar State Hydroelectric Power Corpn. Ltd. plans to set up 8 MW SHEP at Supaul, site for the project has been identified.

December 11, 2010

Hydel Power

Status: Planning
Promoter: Bihar State Hydroelectric Power Corporation Limited
Project Name: Pursa SHEP Project
Capacity: 8 MW
Cost: Rs. 6800 million
Location: Supaul dist. Bihar
Current Status: As of December 2010, work on the project is under planning stage, project site has been identified.


Ramco Industries plans to set up 1, 20,000 mtpa asbestos cement sheet manufacturing unit & 2,00000 mtpa cement grinding plant in Bihar

October 22, 2010

Cement

Status: Planning
Promoter: Ramco Industries Ltd.
Project Name: Asbestos Cement Sheet Manufacturing Unit & Cement Grinding Plant
Capacity: Asbestos Cement Sheet-1, 20,000 mtpa & Cement Grinding Plant-2,00000 mtpa
Location: Industrial Area, Bihiya, Bhojpur, Bihar
Current Status: As of August 2010, work on the project is under planning stage.


Siddhi Refoils & Industries plans to set up a 275 tpd vegetable oil manufacturing unit in Bihar, project entails an investment of Rs. 94 crore, work on the project is likely to commence by June 2010

June 7, 2010

Vegetable Oils

Status: Planning
Commence: June 2010
Promoter: Siddhi Refoils & Industries Private Limited
Project Name: Vegetable Oils Manufacturing Unit
Capacity: 275 tpd
Cost: Rs.94 Crore
Location: Vaishali district of Bihar
Current Status: As of May 2010, work on the project is under planning stage.